Time and studies · free tool
Time Estimates Calibration Calculator
Do you usually set aside two hours and use three? Gather forecasts and actual durations of three completed tasks. The ratio between the totals adjusts a new estimate, making it visible how much the history has deviated from the initial planning.
Free, no sign-up required
In action
See an example
The previous tasks were estimated at 2, 3 and 5 hours, 10 in total. They took 3, 4 and 8 hours, 15 in total. The factor, actual divided by estimated, is 1.5. A new initial estimate of 6 hours becomes 9 hours when adjusted by this history.
Use “Fill in example” to try these fictional values.
How we calculate
- Somamos as horas previstas e realizadas nas três tarefas, mantendo a mesma unidade em todo o histórico.
- Dividimos o total realizado pelo previsto. Não usamos uma média simples das razões de cada tarefa, que daria peso igual a trabalhos de tamanhos diferentes.
- Multiplicamos a nova estimativa pelo fator agregado e exibimos os desvios individuais para você conferir se o conjunto faz sentido.
Comparable history
Compare tasks with a similar scope. A history of short reviews does not represent a long research project. Group work with similar conditions and effort.
If a task grew while you were doing it, the gap may come from that extra work, not from a poor estimate.
Write down the reason before carrying the factor over to the next commitment. The math cannot spot that difference on its own.
What to measure
Use only finished tasks. Entering an activity in progress as if it were done lowers the factor and makes the next estimate too optimistic.
Also choose what to measure and use the same criterion in every row:
- Active effort: only the time you actually worked on the task.
- Elapsed time: from start to finish, including waiting.
Three observations give a limited reference. Keep track of new results and revise the adjustment when the type of work changes.
Questions when filling out
Why not average the three percentages?
A half-hour task would weigh as much as a 10-hour one. The ratio between totals weights the comparison by the planned volume and better describes the combined effort of these 3 tasks.
Is a factor less than 1 allowed?
Yes. It indicates that the recorded time was less than expected as a whole. Check that the scope was actually completed and that you measured durations in the same way before reducing the next commitment.
Sources and further reading
- NASA — Schedule Management Handbook, 2010 (opens in new tab)
Task dependencies, time estimates, and reviewing plans.
Organize everyday life with Focca
Write down how long you expect to spend, then record the actual duration when you finish. Compare the two to plan future tasks better.