Personal project stage planner
Some stages can happen together. Others only start when everything before them is done. Set up 2 independent branches and a shared final stage to see the minimum deadline, the wait of the shorter branch and the slack against the time available.
Free, no sign-up required
In action
See an example
Branch A takes 4 days and branch B, 7. If both can truly run in parallel, the 2-day final stage starts after day 7 and ends after day 9. In sequence, it would take 13 days. With 10 days available, 1 day is left, and branch A waits 3 days for B to finish.
Use “Fill in example” to try these fictional values.
How we calculate
- Consideramos que os ramos A e B começam juntos, com recursos independentes.
- O início da etapa final fica no término do ramo mais longo. Somamos sua duração para obter o prazo mínimo do conjunto.
- Comparamos esse prazo com o tempo disponível e com a execução inteiramente em série. A diferença entre os ramos é a espera do mais curto.
When parallel work holds
Parallel work has to be possible in real life. If the same person must work fully on both stages, putting the branches side by side does not create time.
Parallel makes sense when one stage is with someone else or depends on a wait that frees you for something else. Confirm that independence before using the shorter deadline.
If it does not exist, the sequential duration is the more faithful reference.
Waiting and effort
Waiting is not the same as effort. A branch can take a few hours of work and several calendar days because it depends on an outside reply.
Use the same kind of duration in all three fields: the time between start and finish. Do not mix hours of effort converted into days with days of waiting.
The tool shows the dependency, but it does not predict third-party delays or let the final stage start with something pending.
Questions when filling out
Which branch determines the deadline?
The longest determines when the final step can begin. Reducing a branch that already ends before the other does not shorten the set.
Can I include a margin day?
Yes. Compare the minimum term with an available term that contains this margin. The gap is made explicit. Don't secretly increase all durations and then interpret the result as minimum time.
Sources and further reading
- NASA — Schedule Management Handbook, 2010 (opens in new tab)
Task dependencies, time estimates, and reviewing plans.